Define what both options must deliver
Record the products, expected annual output, target markets, first production date and space needed for expansion. Agree which requirements are essential and which can wait for a second phase. Use these assumptions for both estimates so the comparison survives a change in layout.
Test the building against the equipment
Trace the largest item from the unloading point to its operating position. Check doors, floor loading, ceiling space and access for replacement. For a retrofit, mark any work that would interrupt existing operations. For a new building, check site access and the route to external utilities.
Check actual utility capacity
A drawing showing a chilled-water connection does not tell you how much capacity is available. Compare the proposed load with existing peak demand and usable spare capacity. If records are missing, identify the measurement needed, who will obtain it and which decision depends on it.
Compare costs and dates on the same basis
Include demolition, temporary services, shutdowns and commissioning in the retrofit option. Include external connections, site preparation and local approval milestones in the new-build option. For example, if a retrofit depends on a power upgrade, show the cost and opening date both with and without that upgrade.
Write the investment decision
For each option record the estimated cost range, earliest credible start of production, key assumption, supporting evidence and responsible person. End with a decision to proceed, investigate or set the option aside. Send a site plan, the capacity brief and the largest unresolved constraint for an initial discussion.
Send Your Project Basis for an Initial Technical Discussion
Available information can be incomplete. Label assumptions, identify known gaps and share the documents that can support a focused first review.